Decant Structure Filtering Unit – Awakmas Gold Mining

PETROSEA – INDIKA Energy

Project Information

Project :
Decant Structure Filtering Unit – Awakmas Gold Mining

Client :
PETROSEA – INDIKA Energy

Scope of Work :
Perforated Pipe, Welding & Hot Dip Galvanize

Material

  • Pipe A53 Gr. B 24” sch. 20 ERW
  • Perforated Concrete Steel Structure
  • Slip on Flange A105 24” #150

Fabrication

  • WELDING
  • WPS ASME IX
  • Welding process GTAW+FCAW
  • Welding inspector CSWIP 3.1
  • Welder Disnaker Certified

Coating

  • Reference: Approved HDG Procedure, ASTM A123
  • Coating Inspector Level II BNSP Certified
← Back To Projects